How to Write a Dry Type Transformer Datasheet for EPC RFQs
Dry Type Transformer Datasheet: What an EPC RFQ Must Define
A dry type transformer datasheet can contain forty or fifty technical fields and still fail as an RFQ document.
The problem is usually not the number of parameters. It is the status of those parameters.
Is a value a mandatory purchaser requirement? Is it a supplier proposal? Is it a guaranteed value? Is it still subject to system study? Can it change after the order? And how will it eventually be verified?
These distinctions matter because the datasheet sits between several engineering documents: the single-line diagram, transformer specification, supplier quotation, deviation list, general arrangement drawing, nameplate drawing, test plan and final test reports.
If those documents do not describe the same transformer, a technically attractive quotation can still become a difficult EPC package.
A useful dry type transformer datasheet therefore does more than describe the equipment. It controls the technical basis on which the transformer is quoted, compared, approved and tested.
Treat the Datasheet as a Controlled Engineering Interface
A catalogue answers the question:
âWhat products can this manufacturer supply?â
A project datasheet should answer a different question:
âWhat exact transformer is required for this installation, and what is the supplier committing to provide?â
That difference changes how the document should be written.
The most effective tender schedules normally distinguish between at least four types of information:
| Data Status | Meaning |
|---|---|
| Purchaser requirement | A project condition or required value that the supplier must comply with |
| Supplier to state | Information that must be entered by the bidder for technical evaluation |
| Supplier guaranteed value | Performance or design information that will form part of the accepted technical offer |
| Final approved value | Information frozen after technical clarification and drawing approval |
A separate deviation column is equally valuable.
Without it, a bidder may simply replace the requested value with its normal design value. Procurement may then compare two quotations without noticing that the transformers are technically different.
IEC 60076-11:2018 specifically addresses dry-type transformers within its defined scope and directs enquiry and order information back to the general transformer information framework of IEC 60076-1. In other words, information exchange between purchaser and manufacturer is part of transformer engineering, not an administrative afterthought.
Start With the Project Basis, Not the Manufacturer's Catalogue
Several datasheet fields cannot be selected correctly by the transformer manufacturer alone.
They originate from the electrical system.
These commonly include:
-
rated power or the required operating duty;
-
HV and LV system voltages;
-
system frequency;
-
number of phases;
-
required vector group;
-
tapping requirements;
-
target impedance where dictated by the system study;
-
insulation coordination requirements;
-
earthing arrangement;
-
interface with HV switchgear and LV switchboard;
-
required enclosure and installation conditions.
A supplier may identify a conflict or recommend an alternative, but the project should not expect the manufacturer to infer the network design from the destination country or from the transformer capacity alone.
For example, writing only:
1600 kVA, 11 kV / 0.4 kV, dry type
does not establish whether the transformer will be AN rated, whether an AF rating is required, what impedance the LV fault study assumes, what tapping range is needed, what dielectric insulation levels apply or whether an enclosure is part of the rated configuration.
A price can be produced from limited information.
A controlled technical comparison cannot.
Electrical Ratings: Define What the System Actually Requires
The first section of a dry type transformer datasheet normally establishes the electrical identity of the unit.
Rated Power
State the required rated power and make the associated cooling mode explicit.
This becomes particularly important when both AN and AF ratings are proposed.
A datasheet containing:
Rated power: 1600 kVA
Cooling: AN/AF
is ambiguous unless it also states whether 1600 kVA is the AN rating, the AF rating or both.
Where forced-air operation provides a separately approved rating, list the two ratings independently.
Do not assume a universal AF uprating percentage. The permissible rating depends on the transformer design and its approved thermal performance.
Rated HV and LV Voltage
State the actual transformer winding voltages required by the project.
Do not rely on terminology such as â10 kV system,â â11 kV classâ or â400 V distributionâ if the transformer voltage has not been frozen.
The rated voltage must also be coordinated with:
-
switchgear;
-
cable or busduct ratings;
-
protection;
-
equipment utilization voltage;
-
generator or utility interface;
-
other transformers intended for parallel operation.
For projects where voltage selection itself is still under engineering review, mark the parameter as TBC rather than allowing a supplier assumption to become a hidden design decision.
Frequency and Number of Phases
Frequency should always be stated explicitly.
It affects transformer magnetic design and cannot be treated as a minor purchasing detail.
The number of phases should likewise appear as a controlled field even when a three-phase unit seems obvious from the project context.
Vector Group and Neutral Arrangement
A vector group is not merely a nameplate convention.
It affects phase displacement, grounding arrangements, zero-sequence behaviour and compatibility with existing transformers.
If parallel operation is required, voltage ratio, vector group, tap position and impedance become particularly important.
The datasheet should also identify whether the LV neutral is brought out and any specific neutral-terminal or grounding requirement.
Tapping Arrangement
A useful specification states more than âwith taps.â
It should define, as applicable:
-
which winding is tapped;
-
required tapping range;
-
tapping step;
-
number of positions;
-
whether the tapping device is de-energized or on-load.
For the distribution dry-type transformers commonly used in building and industrial applications, de-energized tapping arrangements are frequently encountered, but the project datasheet should state the required arrangement instead of relying on convention.
Short-Circuit Impedance
Impedance deserves its own guaranteed field.
It influences prospective fault current, voltage regulation, motor-starting voltage dip and parallel load sharing.
A consultant who has designed the LV system around a specified transformer impedance should not allow the value to be replaced silently by a manufacturer's standard design.
If the required impedance remains under study, mark it clearly.
If it has been fixed, require the bidder to state the guaranteed value and identify any deviation.
A detailed discussion of impedance selection belongs in a separate impedance study; the datasheet's job is to preserve the approved requirement.
Do Not Combine Thermal Class, Temperature Rise and Insulation Level
Three different concepts are frequently collapsed into one line of transformer specifications:
Insulation: Class F
That is not enough.
The datasheet should distinguish between dielectric insulation requirements and thermal insulation requirements.
For the dielectric side, the project may need fields such as:
-
highest voltage for equipment, Um;
-
applicable power-frequency withstand level;
-
lightning impulse withstand requirement;
-
insulation requirements for HV and LV windings.
IEC 60076-3 addresses transformer insulation requirements, dielectric tests and external clearances within its applicable scope.
The thermal side should separately identify:
-
winding insulation-system thermal class;
-
specified winding temperature-rise requirement;
-
cooling mode;
-
ambient-temperature basis;
-
altitude;
-
any special thermal operating duty.
A Class F or Class H designation does not by itself define the transformer's dielectric withstand level, nor should a higher insulation thermal class automatically be interpreted as permission for a higher project temperature rise.
Site Conditions Belong on the Datasheet
Transformer rating is meaningful only against defined service conditions.
A project datasheet should therefore record the operating environment before the supplier finalizes the thermal and dielectric design.
Depending on the project, relevant information can include:
| Site Information | Why It Matters |
|---|---|
| Installation altitude | Can affect cooling and dielectric design |
| Maximum/minimum ambient temperature | Establishes thermal and environmental design conditions |
| Indoor/outdoor installation | Changes enclosure and exposure requirements |
| Humidity/condensation risk | May affect insulation and enclosure provisions |
| Dust or contamination | May affect insulation surfaces and ventilation strategy |
| Coastal/corrosive environment | May affect enclosure materials and coating |
| Transformer-room ventilation | Influences heat rejection |
| Access restrictions | Can determine final dimensions and assembly arrangement |
| Seismic requirement | Must be identified where applicable to the project |
IEC 60076-11:2018 specifically addresses enclosure performance and management of thermal and dielectric features with altitude, and it includes climatic, environmental, fire-behaviour and seismic provisions within its scope. These classifications should be specified when the project requires them; they should not be copied automatically into every RFQ.
Specify the Enclosed Transformer, Not Just the Active Part
For an enclosed dry-type transformer, the datasheet should make clear whether the quoted rating and guaranteed thermal performance apply to the complete transformer with the specified enclosure fitted.
This prevents a common ambiguity:
Transformer rating: compliant.
Enclosure rating: compliant.
Transformer plus enclosure: thermal performance not clearly defined.
An IP rating does not establish cooling capability.
Likewise, enclosure ventilation does not establish ingress protection unless the complete assembly satisfies the required arrangement.
Where the project specifies an IP code, reference the required protection separately from thermal performance and describe the installation exposure. IEC 60529 provides the IP classification framework, while transformer thermal performance remains a separate design question.
The final GA drawing should later resolve:
-
ventilation openings;
-
access panels;
-
cable entries;
-
busduct connections;
-
removable covers;
-
base openings;
-
fan arrangements;
-
site-installed closures.
Guaranteed Performance Data Should Be Comparable
A tender datasheet is also the place where procurement prevents misleading price comparisons.
Two 1600 kVA transformers can share the same basic voltage and vector group while differing materially in:
-
no-load loss;
-
load loss;
-
impedance;
-
sound level;
-
winding material;
-
cooling configuration;
-
enclosure;
-
dimensions;
-
accessories;
-
test scope.
The bidder should therefore return the guaranteed or offered performance data required by the project.
Typical fields may include:
No-load loss
State the guaranteed value and relevant rated condition.
Load loss
The reference temperature and applicable winding/material basis matter. Values quoted under different reference conditions should not be compared as if they were identical.
No-load current
Useful for technical comparison and final test verification where specified.
Short-circuit impedance
State the tapping/reference condition where necessary.
Sound level
If the project has an acoustic limit, specify the required quantity and measurement basis rather than writing only âlow noise.â IEC 60076-10 provides transformer sound measurement methods and is primarily intended for factory measurement.
Efficiency
If efficiency is a procurement requirement, define the applicable loading, power factor, temperature/reference conditions or regulatory basis. A percentage without a defined operating point can be misleading.
Dimensions and mass also matter, but they should carry an appropriate document status. Tender-stage dimensions may be preliminary; dimensions frozen in an approved GA drawing become an interface requirement.
Interfaces and Accessories Are Part of the Equipment Definition
Some of the most expensive EPC problems occur outside the windings.
A transformer can be electrically correct and still fail site coordination because the terminal arrangement, cable entry or control voltage does not match the project.
The datasheet should therefore include the relevant mechanical and control interfaces.
For the HV side, identify whether the interface is cable, busbar or another approved arrangement and define the required entry direction where necessary.
For the LV side, identify whether connection is by cable or busduct. If a busduct is used, the transition arrangement and supplier boundaries should be coordinated on drawings.
Other fields may include:
-
HV and LV terminal position;
-
neutral terminal;
-
protective earthing terminals;
-
cable-entry direction;
-
gland plates;
-
lifting points;
-
rollers or base arrangement;
-
enclosure material and coating requirement;
-
temperature sensors;
-
temperature controller;
-
cooling fans;
-
fan control arrangement;
-
alarm and trip contacts;
-
communication outputs where required;
-
auxiliary supply voltage and frequency;
-
anti-condensation heater where specified.
Do not require accessories merely because they appear in another project's datasheet. Every field should correspond to an actual operating, protection, maintenance or interface requirement.
Separate the Test Schedule From the Datasheet Values
A datasheet defines what the transformer must be.
The inspection and test plan defines how agreed characteristics will be verified.
They are connected, but they are not the same document.
For dry-type transformers within its scope, IEC 60076-11:2018 classifies the following as routine tests:
-
measurement of winding resistance;
-
measurement of voltage ratio and check of phase displacement;
-
measurement of short-circuit impedance and load loss;
-
measurement of no-load loss and current;
-
applied-voltage withstand test;
-
induced-voltage withstand test;
-
partial-discharge measurement under the applicable provisions.
The standard identifies full-wave lightning impulse and temperature-rise testing as type tests.
Its special-test group includes, among other items, sound-level measurement, short-circuit testing, climatic testing, environmental testing, fire-behaviour testing and seismic testing.
This distinction prevents several tender errors.
A temperature-rise test should not automatically be written into the routine-test column.
A sound measurement should not automatically be assumed to occur on every transformer unless required by the contract.
The routine short-circuit impedance measurement is not the same thing as a physical short-circuit withstand test.
FAT Is Not a Fourth IEC Test Classification
Routine, type and special describe test classification.
FAT describes a contractual acceptance activity.
A FAT may include:
-
witnessing routine tests;
-
reviewing type-test reports;
-
witnessing specified special tests;
-
functional checks;
-
accessory verification;
-
visual inspection;
-
document review;
-
nameplate verification;
-
dimensional checks;
-
checking the manufactured equipment against approved drawings.
This distinction should be reflected in the RFQ.
Instead of writing only:
FAT required
state what the purchaser expects to witness, what reports must be submitted, whether third-party inspection is required, and what acceptance documents are needed.
Add a Supplier Deviation Column
One of the simplest improvements to an EPC transformer datasheet is also one of the most effective:
add a dedicated Deviation / Comment column.
A useful tender format is:
| Parameter | Purchaser Requirement | Supplier Offered / Guaranteed | Deviation / Comment |
|---|---|---|---|
| Rated power | Project requirement | Supplier to state | |
| HV voltage | Project requirement | Supplier to confirm | |
| LV voltage | Project requirement | Supplier to confirm | |
| Vector group | Project requirement | Supplier to confirm | |
| Impedance | Project requirement | Guaranteed value | |
| No-load loss | Maximum if specified | Guaranteed value | |
| Load loss | Maximum if specified | Guaranteed value | |
| Enclosure | Project requirement | Supplier to state | |
| Dimensions | Interface limit if applicable | Supplier preliminary/final value | |
| Test scope | Project requirement | Included/excluded |
If a supplier cannot comply with a requirement, the difference should appear in the deviation columnânot disappear inside the supplier's revised datasheet.
This is particularly important when commercial teams compare bids.
A lower price may be associated with a different loss level, winding material, enclosure, test scope or accessory package.
Until those differences are normalized, it is not a like-for-like comparison.
A Practical EPC Dry Type Transformer Datasheet Structure
There is no single universal datasheet format for every project, but the following structure provides a useful engineering basis.
1. Project and Document Information
| Field | Datasheet Treatment |
|---|---|
| Project name | Purchaser |
| Equipment tag number | Purchaser |
| Quantity | Purchaser |
| Service/application | Purchaser |
| Installation location | Purchaser |
| Applicable specification | Purchaser |
| Applicable IEC / local standards | Purchaser |
| Datasheet revision/status | Document control |
2. Basic Electrical Data
| Field | Datasheet Treatment |
|---|---|
| Transformer type | Requirement / supplier confirmation |
| Rated power, AN | Purchaser requirement or supplier proposal |
| Rated power, AF if applicable | Supplier guaranteed value / project requirement |
| Number of phases | Purchaser |
| Frequency | Purchaser |
| HV rated voltage | Purchaser |
| LV rated voltage | Purchaser |
| Vector group | Purchaser or approved supplier proposal |
| HV tapping range | Purchaser |
| Tapping arrangement | Purchaser / supplier confirmation |
| Short-circuit impedance | Project requirement + supplier guarantee |
| Neutral arrangement | Purchaser |
3. Dielectric and Thermal Requirements
| Field | Datasheet Treatment |
|---|---|
| Highest voltage for equipment, Um | Project requirement |
| HV dielectric withstand requirements | Project requirement |
| LV dielectric requirements | Project requirement |
| Winding insulation thermal class | Project requirement / supplier proposal |
| Winding temperature rise | Project requirement / supplier guarantee |
| Cooling method | Project requirement / supplier confirmation |
| AN/AF duty | Clearly separated |
| Installation altitude | Purchaser site data |
| Ambient conditions | Purchaser site data |
4. Performance Guarantees
| Field | Datasheet Treatment |
|---|---|
| No-load loss | Supplier guaranteed |
| Load loss | Supplier guaranteed with reference condition |
| No-load current | Supplier guaranteed where required |
| Impedance | Supplier guaranteed |
| Sound level | Limit + supplier guarantee where required |
| Efficiency | Defined calculation condition if required |
5. Construction and Installation
| Field | Datasheet Treatment |
|---|---|
| Winding conductor material | Requirement or supplier declaration |
| Core type/material if specified | Requirement or supplier declaration |
| Indoor/outdoor | Purchaser |
| Enclosure/IP rating | Purchaser requirement |
| Enclosure material/coating | Project-specific |
| HV connection | Interface requirement |
| LV connection | Interface requirement |
| Cable entry | Interface requirement |
| Approximate dimensions | Supplier tender data |
| Final dimensions | Approved GA |
| Approximate/final mass | Supplier |
6. Monitoring and Accessories
| Field | Datasheet Treatment |
|---|---|
| Winding temperature sensors | Requirement |
| Temperature controller | Requirement / supplier details |
| Fan system | Requirement / supplier details |
| Fan-start function | Supplier design / approved logic |
| High-temperature alarm | Project interface |
| Trip contact | Project interface |
| Auxiliary supply | Purchaser / supplier coordination |
| Communication requirements | Project-specific |
7. Testing and Documentation
| Field | Datasheet Treatment |
|---|---|
| Routine tests | Applicable standard |
| Type-test evidence | Purchaser requirement |
| Special tests | Specify individually |
| FAT witness | Yes/no and witness scope |
| Third-party inspection | Project-specific |
| Test reports | Required deliverable |
| GA drawing | Required deliverable |
| Wiring diagram | Required where applicable |
| Nameplate drawing | Required for approval if specified |
| O&M documentation | Contract requirement |
| Deviation schedule | Mandatory for controlled bid review |
This table should be adapted to the project. It is not a substitute for the applicable IEC standard, consultant specification or national utility requirements.
Do Not Fill Unknown Fields With âStandardâ
âStandardâ is one of the most dangerous words in a technical tender schedule.
Standard according to whom?
The consultant?
The utility?
IEC?
The supplier's normal factory design?
The destination country's common practice?
If a parameter genuinely remains open, use a controlled status such as:
Supplier to propose
Supplier to state
TBC by purchaser
To be confirmed after system study
Subject to GA approval
These labels preserve the engineering decision.
Writing âstandardâ often hides it.
Freeze the Datasheet Before Production Release
A purchase order does not necessarily mean that every technical parameter is ready for manufacture.
The project should define a technical approval point after which critical parameters cannot change without formal revision.
Before manufacturing release, cross-check the approved datasheet against at least the relevant:
-
single-line diagram;
-
technical offer;
-
deviation schedule;
-
purchase order;
-
GA drawing;
-
connection or terminal drawing;
-
control wiring diagram;
-
nameplate drawing;
-
approved test schedule.
Voltage, vector group, tapping, impedance, cooling, enclosure and interface data should tell the same story across the package.
For example, if the technical offer says 11 kV / 415 V while the final datasheet says 11 kV / 400 V, the problem is not a clerical typo.
It changes the equipment being manufactured.
Likewise, if the datasheet requires IP23 but the GA drawing shows an enclosure configuration based on another protection requirement, production should not proceed until the discrepancy is formally resolved.
Document consistency is part of equipment engineering.
How Procurement Should Compare Supplier Datasheets
Price comparison should follow technical normalization, not precede it.
Before comparing commercial totals, place each bid against the same project requirements and check at least four things.
First, identify explicit deviations.
Second, identify blank fields. A blank guarantee should not automatically be interpreted as compliance.
Third, identify supplier assumptions. They may appear in footnotes, quotation exclusions or catalogue pages rather than the technical schedule.
Fourth, check whether guaranteed values are stated under equivalent conditions.
A technically useful comparison may reveal that:
Supplier A has lower price but excludes a required enclosure.
Supplier B includes the enclosure but offers a different impedance.
Supplier C complies electrically but quotes type testing separately.
Supplier D provides a lower loss value, but under a different reference condition.
The commercial ranking can change after those differences are corrected.
Five Datasheet Errors That Commonly Create EPC Problems
1. Capacity Is Stated Without the Cooling Basis
AN and AF ratings become mixed, leaving the actual continuous rating unclear.
2. âInsulation Classâ Is Used for Both Thermal and Dielectric Requirements
This can leave the required Um, impulse withstand and power-frequency withstand requirements undefined.
3. The Datasheet Has No Deviation Column
Supplier substitutions become difficult to identify during technical bid evaluation.
4. Site Conditions Are Missing
Altitude, ambient temperature, enclosure and ventilation assumptions are then introduced by the supplier instead of controlled by the project.
5. Test Requirements Are Written Only as âIEC Tests + FATâ
No one knows whether temperature rise, sound, impulse, short-circuit or other verification is actually required on the project unit.
Each of these problems is easier to correct before tender award than after manufacturing begins.
The Best Datasheet Is Not the Longest One
A technically disciplined transformer datasheet does not try to prescribe every manufacturing detail.
The purchaser should control parameters that affect the electrical system, installation interfaces, performance requirements and acceptance criteria.
The manufacturer should retain responsibility for detailed design within those requirements.
Over-specification can be as problematic as under-specification.
Prescribing unnecessary internal construction details may restrict technically valid designs without improving project performance.
Leaving system-critical requirements undefined does the opposite: it transfers project decisions to the supplier unintentionally.
The objective is to define the boundary correctly.
That is what makes a dry type transformer datasheet useful throughout the EPC processâfrom RFQ to technical bid evaluation, drawing approval, manufacturing and FAT.
FAQ
Is a dry type transformer datasheet the same as a technical specification?
No. The technical specification usually establishes general design, standards, quality, documentation and project requirements. The datasheet records the project-specific values and supplier guarantees for an individual transformer or equipment group. They should be read together.
Which values should the supplier guarantee in the datasheet?
The required scope depends on the project, but guaranteed data commonly include parameters such as impedance, losses, temperature-rise performance, sound level where specified, rated cooling conditions and other performance requirements defined in the tender. Purchaser-controlled electrical and site requirements should normally remain identifiable as such.
Should dimensions be fixed during the RFQ stage?
Not always. Tender dimensions may be preliminary. Where room size, door access, cable position or busduct alignment creates a hard interface, the purchaser should define the available limits and require final dimensions to be frozen through the approved GA drawing before manufacture.
Is a temperature-rise test part of routine FAT testing?
Under IEC 60076-11:2018, temperature-rise testing is classified as a type test rather than a routine test. If the purchaser requires a project-unit temperature-rise test or specific witnessed evidence, that requirement should be defined in the order and test plan.
Is short-circuit impedance testing the same as a short-circuit withstand test?
No. Measurement of short-circuit impedance and load loss is a routine test under IEC 60076-11. A physical short-circuit test is classified separately as a special test. The two should not be confused in an FAT schedule.
CTA
If you are preparing an EPC enquiry for a dry-type transformer, send the project datasheet, single-line diagram or technical specification together with the required kVA, HV/LV voltages, frequency, vector group, impedance requirement, installation conditions, cooling arrangement and enclosure requirement.