A dry-type transformer can meet the required kVA rating, voltage ratio and vector group and still create installation problems when it reaches the project site.
The difficulty is often found at the connection interface. High-voltage and low-voltage terminals may face the wrong direction for the planned cable route. The available space may not accommodate the required cable bending radius. A low-voltage busduct may approach the transformer from a different elevation than the terminal connection was designed for.
These are not minor installation details. They affect the transformer enclosure, cable termination arrangement, connection supports and the final electrical room layout.
A dry type transformer terminal arrangement should therefore be reviewed as part of the electrical and mechanical interface design, rather than treated as a detail that can be resolved after the transformer has been manufactured.
This guide examines the physical arrangement of HV and LV terminals, cable entry options, cable and busbar connections, and the information that should be confirmed before approving the manufacturer's general arrangement drawing.
1. What Does Dry Type Transformer Terminal Arrangement Mean?
Terminal arrangement describes the physical location, orientation and connection configuration of the transformer terminals.
It is useful to distinguish three related but different engineering concepts.
Electrical connection configuration
This defines how the transformer windings are connected electrically. It includes the vector group, phase relationships, neutral availability and winding connection arrangement.
Physical terminal arrangement
This describes where the HV and LV terminals are positioned on the transformer, their relative heights, orientation, phase identification and accessible connection surfaces.
External connection interface
This covers how external cables, cable lugs, busbars or busducts connect to the transformer. It also includes cable entry openings, gland plates, connection supports and the available working space.
These three aspects must agree, but they should not be treated as interchangeable.
For example, a transformer with a Dyn11 vector group does not automatically have a particular left-to-right terminal layout. The vector group identifies the electrical phase relationship, while the approved connection drawing defines the actual terminal identification and physical arrangement.
HV and LV should also be distinguished from primary and secondary. HV and LV refer to winding voltage levels, whereas primary and secondary describe the electrical role of a winding in the particular application.
2. Is There a Standard HV/LV Terminal Layout?
There is no single physical terminal layout that should be assumed for every dry-type transformer.
Depending on the transformer design, terminals may be arranged as:
-
Exposed connection pads or terminal rods.
-
Insulated terminal assemblies.
-
Horizontal or vertical busbar connections.
-
Dedicated cable termination compartments.
-
Separate HV and LV connection zones within an enclosure.
The actual arrangement depends on rated voltage, current, winding construction, insulation requirements, enclosure design and the intended connection method.
For this reason, a catalogue photograph is not sufficient for installation approval.
The manufacturer should provide a drawing showing the transformer from clearly identified viewing directions. The drawing should establish the front reference, HV and LV terminal positions, phase identification, terminal heights and the relevant connection dimensions.
This becomes particularly important when the transformer is installed between existing medium-voltage switchgear and a low-voltage distribution board. Both interfaces must be coordinated before the final transformer arrangement is released for manufacture.
3. Cable Entry Direction: Top, Bottom or Side?
Cable entry direction is one of the first decisions that should be confirmed during project coordination.
The most suitable arrangement depends on the building cable route, transformer enclosure, ventilation openings and available termination space.
| Cable entry arrangement | Typical application | Main engineering checks |
|---|---|---|
| Top entry | Overhead cable trays or top-mounted connection zones | Roof clearance, cable support, ventilation and gland plate access |
| Bottom entry | Underground cable trenches or raised-floor installations | Trench position, foundation openings and cable bending radius |
| Side entry | Side-mounted cable trays or designated side access | Wall clearance, access space and ventilation openings |
| Front/rear entry | Enclosure-specific access arrangements | Approved entry zones, internal routing and maintenance access |
Top cable entry
Top entry can be practical when the cable tray is installed above the transformer and the terminal arrangement supports an overhead connection.
However, the top of a dry-type transformer may also contain ventilation outlets, lifting provisions or maintenance access points.
Cable openings should not be introduced into an area that interferes with the designed airflow or structural arrangement.
The manufacturer should confirm the permitted gland plate position and cable routing before the enclosure is modified.
Bottom cable entry
Bottom entry is frequently considered for projects with underground cable trenches or raised electrical floors.
Its main advantage is that cables can approach the transformer from below without requiring overhead cable routes.
The available space beneath the terminals must still be checked carefully.
A cable trench may be correctly positioned on the civil drawing but leave insufficient space for the actual cable bending radius, termination lugs or installation tools.
The transformer base, foundation openings and cable trench should therefore be reviewed together.
Side cable entry
Side entry can provide a practical route when the cable ladder or tray is located beside the transformer.
ABB's installation guide for its ventilated dry-type transformer range recommends side cable entry because it helps keep ventilation areas unobstructed.
That recommendation is specific to the covered product range, not a universal requirement for all dry-type transformers.
The selected entry position must follow the manufacturer's enclosure design and approved drawings.
4. Cable Connection or Busbar Connection?
The LV side of a dry-type transformer can be connected through power cables or a busbar/busduct system.
The correct choice depends on the rated current, available installation space, distribution arrangement and project design.
Cable connection
When cables are used, the connection design should establish:
-
Cable conductor material: copper or aluminium.
-
Cable type and insulation specification.
-
Number of parallel cable runs per phase.
-
Cable cross-sectional area.
-
Cable lug material and terminal compatibility.
-
Terminal pad dimensions and bolt-hole arrangement.
-
Cable entry position and bending space.
-
Cable support and termination arrangement.
A cable terminal should not carry unnecessary mechanical loads from unsupported cable weight or installation tension.
The cables should be supported independently in a way that prevents excessive force from being transferred to the transformer terminal assembly.
The terminal connection torque must follow the transformer manufacturer's instructions and the connector manufacturer's requirements. A generic torque value should not be applied to every terminal.
Busbar or busduct connection
For projects using a low-voltage busduct, the transformer terminal arrangement must be coordinated with the busduct interface drawing.
The review should include:
-
Busduct connection elevation.
-
Phase sequence and phase arrangement.
-
Neutral and protective earth connections.
-
Terminal pad dimensions and bolt pattern.
-
Required transition busbars.
-
Flexible connection requirements.
-
Independent mechanical support.
-
Allowance for alignment and thermal movement.
A busduct that reaches the transformer physically may still be unsuitable if its connection pads, phase arrangement or mechanical support do not match the transformer design.
Where appropriate, flexible connectors can reduce the transfer of mechanical stress and vibration into the transformer winding connection. Their use and configuration must be confirmed by the transformer and busduct manufacturers.
5. Why LV Terminal Arrangement Often Requires More Space
The low-voltage side can present a greater physical connection challenge because its rated current is substantially higher than the HV current at the same transformer capacity.
For a balanced three-phase transformer, rated line current can be calculated using:
[
I=\frac{S}{\sqrt{3}\times V}
]
Where:
-
(I) = rated line current in amperes.
-
(S) = rated apparent power in VA.
-
(V) = rated line-to-line voltage in volts.
Consider a hypothetical 1600 kVA transformer with an 11 kV HV winding and a 400 V LV winding.
HV rated current:
[
I_{HV}=\frac{1600000}{\sqrt{3}\times11000}
\approx84A
]
LV rated current:
[
I_{LV}=\frac{1600000}{\sqrt{3}\times400}
\approx2309A
]
The LV current is approximately 27.5 times the HV current.
This difference explains why LV connections may require several parallel cable runs, larger terminal pads or a busduct interface.
It also affects the available connection space.
A transformer drawing that shows the terminal positions without indicating the intended cable or busbar arrangement may not provide enough information for installation planning.
The final connection design must also account for cable ampacity, installation conditions, temperature correction, short-circuit withstand requirements and the limits of the terminal assembly.
6. Cable Bending Radius, Mechanical Support and Electrical Clearance
Cable bending radius is an important dimension in the terminal arrangement.
A large cable cannot always turn immediately after leaving the terminal. Its minimum bending radius depends on the cable construction, conductor size, insulation, manufacturer specifications and installation conditions.
There is no single bending-radius value that applies to every transformer cable connection.
The transformer outline drawing should provide enough space for the actual cable route, including:
-
The distance between the terminal pad and cable entry.
-
The space required for cable lugs.
-
The cable's minimum bending radius.
-
The available installation and maintenance space.
-
The position of cable supports and cleats.
ABB's installation instructions specifically require cable entry to follow the outline drawing so that the required bending radius can be maintained.
Mechanical support deserves equal attention.
Cable weight, pulling tension and forces during installation should not be transferred directly to the transformer terminal assembly. Cable cleats and supports must also be selected for the electrical and mechanical conditions of the installation, including the applicable short-circuit duty.
Electrical clearance must remain adequate after the cable lugs and connectors have been installed.
The connection arrangement should preserve the required separation between live parts, adjacent phases and grounded enclosure components.
Where single-core AC cables pass through metal gland plates, the phase grouping and opening arrangement also need review. ABB's installation guide includes specific precautions against enclosure heating caused by unsuitable conductor routing through multiple openings. The approved manufacturer's detail should be followed rather than improvising the cable arrangement on site.
7. Neutral, Earthing and Phase Identification
Neutral and protective earth terminals serve different electrical functions.
A neutral terminal is associated with the winding connection and is provided where the transformer design and project requirements call for an accessible neutral point.
The protective earthing terminal connects the transformer enclosure or designated metallic parts to the protective earthing system.
These connections should be shown separately on the approved drawings.
The project engineer should confirm:
-
Whether the LV winding is star-connected.
-
Whether a neutral terminal is required.
-
The required neutral connection and rating.
-
The project's neutral earthing arrangement.
-
The enclosure protective earth connection.
-
The identification of each phase terminal.
Phase identification must agree with the transformer connection diagram and the project single-line diagram.
Do not determine phase sequence from a generic transformer photograph or assume that the physical left-to-right arrangement is identical across different manufacturers.
The manufacturer's terminal identification and nameplate connection information should govern installation and commissioning.
8. What Should the GA Drawing Show?
The general arrangement drawing should be treated as a controlled interface document.
For a transformer connected through cables or busduct, the drawing should contain sufficient information for the electrical, mechanical and civil teams to coordinate the installation.
| Drawing information | What should be verified |
|---|---|
| Front and side views | Drawing orientation and access reference |
| HV terminal arrangement | Position, phase identification and connection dimensions |
| LV terminal arrangement | Position, current connection interface and phase sequence |
| Neutral terminal | Position and connection requirement |
| Earthing terminal | Enclosure grounding point |
| Terminal pad details | Dimensions, bolt holes and connection hardware |
| Cable entry | Top, bottom or side entry and permitted opening zones |
| Gland plate | Position, dimensions and entry arrangement |
| Cable space | Cable bending radius and installation access |
| Busduct interface | Connection elevation, phase arrangement and bolt pattern |
| Enclosure | Ventilation openings, doors and service access |
| Mechanical arrangement | Base, foundation interface and cable support coordination |
The transformer GA drawing should be reviewed alongside the following project documents:
-
Electrical single-line diagram.
-
Transformer technical datasheet.
-
HV switchgear arrangement drawing.
-
LV switchboard or busduct interface drawing.
-
Cable schedule and cable routing layout.
-
Transformer room general arrangement drawing.
Approving the transformer drawing independently of the surrounding electrical equipment can leave important interface dimensions unresolved.
9. Information to Confirm Before Sending an RFQ
A technically useful RFQ should provide more than the transformer capacity and voltage ratio.
For terminal arrangement review, the following information is particularly valuable.
Electrical information
-
Rated capacity.
-
HV and LV voltage.
-
Frequency.
-
Vector group.
-
Required neutral arrangement.
-
Rated current and applicable system requirements.
Connection information
-
HV cable or busbar connection.
-
LV cable or busduct connection.
-
Cable conductor material.
-
Cable size and number of parallel runs.
-
Cable outside diameter and minimum bending radius.
-
Terminal lug and busbar connection requirements.
Site information
-
Transformer installation orientation.
-
Cable trench or cable tray position.
-
Preferred cable entry direction.
-
Available installation space.
-
Enclosure requirements.
-
Relevant site and local electrical regulations.
Project drawings
-
Single-line diagram.
-
Transformer room layout.
-
Switchgear connection drawing.
-
Busduct interface drawing, where applicable.
If these documents are not yet available, the purchaser should at least identify the intended cable entry direction and connection method.
The final terminal arrangement should be frozen through technical clarification and approved drawings before manufacturing begins.
10. Installation Verification and FAT Considerations
Terminal arrangement verification should not be confused with the transformer's electrical performance tests.
Routine tests verify the specified electrical characteristics under the applicable standard. Type tests and special tests have their own defined purposes and contractual requirements.
They should not automatically be assumed to verify the project's cable entry dimensions, cable bending space or busduct alignment.
If these physical interfaces are important to the project, the purchaser should include dimensional verification and visual inspection in the agreed inspection and test plan.
Before site energization, qualified personnel should verify:
-
HV and LV terminal identification.
-
Phase sequence and connection arrangement.
-
Correct cable lug and busbar installation.
-
Tightening torque according to approved instructions.
-
Cable support and mechanical stability.
-
Required electrical clearances.
-
Protective earthing connections.
-
Cable entry sealing and enclosure integrity.
-
Unobstructed ventilation openings.
All connection work and inspection requiring access to hazardous live parts must be performed under the applicable isolation, discharge, earthing and electrical safety procedures.
The objective is not simply to confirm that the transformer terminals can be connected. It is to confirm that the completed connection arrangement is compatible with the approved electrical and mechanical design.
Frequently Asked Questions
1. Is there a standard HV/LV terminal arrangement for all dry-type transformers?
No. Terminal positions depend on transformer design, winding configuration, enclosure construction and connection requirements. The approved manufacturer's GA drawing should define the actual arrangement.
2. Can a dry-type transformer use top cable entry?
Yes, where the transformer enclosure and terminal design permit it. The cable opening must not interfere with ventilation, lifting provisions or other designated access areas. The manufacturer's approved drawing should identify the permitted entry position.
3. Can the LV side of a dry-type transformer connect directly to a busduct?
Yes, if the transformer terminal arrangement and busduct interface are designed to match. Connection elevation, phase arrangement, bolt pattern, mechanical support and any required flexible connections should be confirmed before manufacture.
4. Does the vector group determine the physical position of HV and LV terminals?
No. The vector group defines the electrical phase relationship between transformer windings. The physical terminal positions and connection points are established by the manufacturer's design and approved connection drawings.
5. What information is required to confirm the terminal arrangement before ordering?
The most useful information includes the transformer datasheet, single-line diagram, intended cable or busduct connection, cable entry direction, cable schedule, available installation space and relevant switchgear interface drawings.
Request a Dry-Type Transformer Technical Review
For EPC projects, industrial facilities and power distribution installations, terminal arrangement should be confirmed before the transformer design is released for manufacturing.
If your project requires a particular HV/LV terminal orientation, cable entry direction or busduct connection, provide the transformer specification and available installation drawings for review.
Contact Henan Huamei Electric Technology Co., Ltd. to discuss your dry-type transformer requirements and the technical information needed for the proposed connection arrangement.
Website: https://www.hnhmelectrical.com/