Leave Your Message
News Categories
Featured News

Transformer RFQ Template: What Information Should Buyers Prepare?

2026-07-15

Many transformer inquiries sent to Chinese manufacturers contain only one sentence:“Please quote a 1000 kVA transformer.”That is not enough for a reliable technical and commercial offer.

A 1000kVA unit for an 11kV urban distribution network may require a different insulation level, terminal arrangement, impedance, enclosure and accessory package from a 1000kVA unit used in a mine, solar plant or coastal industrial facility.

A complete transformer RFQ template should explain where the transformer will operate, what system it will connect to, what load it will supply, which standard applies, how it will be tested and how it must be shipped.

Accurate RFQ data reduces technical clarification, drawing revisions, quotation changes and delivery delays.

transformer RFQ template.webp

Why a Transformer Cannot Be Quoted by Capacity Alone

Transformer pricing is based on more than rated kVA.

Before preparing a transformer quotation, the manufacturer normally needs three groups of information.

The first group covers electrical data:

  • Rated capacity
  • HV voltage
  • LV voltage
  • Frequency
  • Phase
  • Vector group
  • Impedance
  • Tap range

The second group defines the product configuration:

  • Oil-immersed or dry-type
  • Step-up or step-down
  • Indoor or outdoor
  • Standalone transformer or package substation
  • Cooling method
  • Enclosure and terminal arrangement

The third group covers delivery scope:

  • Applicable standard
  • Accessories
  • Routine tests
  • FAT requirements
  • Drawings
  • Export packing
  • Shipping destination
  • Trade terms

Common buyer questions include:

  • We know the connected load but not the required transformer capacity. What should we provide?
  • Should the LV voltage be 400V, 415V or 433V?
  • Can a 10kV transformer be used on an 11kV network?
  • Is Dyn11 mandatory?
  • Does the quotation include HV and LV cable boxes?
  • Is FAT included in the price?
  • Will the radiators be removed for shipping?
  • Does export packing include a wooden case?

These questions should be resolved before the purchase order, not after production starts.

transformer specification checklist.webp

Provide Basic Project Information

A professional transformer inquiry should begin with the project background.

Provide:

  • Project name
  • Project country
  • Installation city or region
  • Application
  • Required quantity
  • Planned delivery date
  • Destination port
  • Final project location

Typical applications include:

  • Factory power distribution
  • Commercial buildings
  • Hospitals
  • Data centers
  • Water treatment plants
  • Mines
  • Cement plants
  • Steel plants
  • Solar power plants
  • Wind projects
  • Utility distribution networks
  • EPC substations

Project information helps the factory determine whether the unit needs a standard distribution design, heavy-duty industrial design, low-loss design, high-altitude correction or enhanced corrosion protection.

A 1000 kVA oil immersed transformer installed in a city commercial district may not use the same enclosure, coating, fittings or packing as one installed at a remote mining site.

transformer FAT test.webp

State the Rated Capacity or Supply Load Data

Transformer capacity is normally stated in kVA or MVA.

Common distribution ratings include:

  • 100 kVA
  • 250 kVA
  • 500 kVA
  • 630 kVA
  • 800 kVA
  • 1000 kVA
  • 1250 kVA
  • 1600 kVA
  • 2000 kVA
  • 2500 kVA

When the design is complete, provide the required transformer rated capacity directly.

When capacity has not been finalized, provide:

  • Total connected load
  • Maximum demand
  • Diversity factor
  • Power factor
  • Motor load percentage
  • Largest motor rating
  • Motor starting method
  • VFD, rectifier, UPS or nonlinear load percentage
  • Future expansion allowance

Consider a processing plant with 900kW of connected equipment. The equipment does not all operate at the same time. If maximum demand is 650kW, power factor is 0.85 and a 15% expansion margin is required, the transformer should be sized from demand, power factor and operating margin rather than from connected load alone.

For large motor loads, also provide:

  • Largest motor output
  • Direct-on-line, soft starter or VFD starting
  • Starts per hour
  • Permitted voltage drop during starting

This information affects transformer sizing for industrial loads and impedance selection.

Specify Both HV and LV Voltages

Voltage mismatch is one of the most common RFQ errors.

Provide:

  • Rated HV voltage
  • Rated LV voltage
  • Highest voltage for equipment
  • Intermediate winding voltage, when required
  • Step-up or step-down duty
  • Grid voltage fluctuation range

Typical voltage ratios include:

  • 10kV / 0.4kV
  • 11kV / 0.415kV
  • 20kV / 0.4kV
  • 22kV / 0.415kV
  • 33kV / 0.415kV
  • 33kV / 11kV
  • 0.8kV / 33kV
  • 0.69kV / 33kV

A 10kV rating should not be assumed to be interchangeable with an 11kV rating.

Winding design, bushings, clearances, insulation coordination and test voltage depend on the rated voltage and highest voltage for equipment.

The LV side also requires an exact value. “400V system” may refer to:

  • 380V
  • 400V
  • 415V
  • 433V
  • 440V
  • 480V
  • 690V

A transformer manufactured for 400V cannot be treated as a 415V unit by changing the nameplate.

Correct transformer voltage matching must be completed before design approval.

Confirm Frequency, Phase and Neutral Arrangement

Provide:

  • 50Hz or 60Hz
  • Single-phase or three-phase
  • Three-wire or four-wire system
  • Whether an LV neutral is required
  • Whether the neutral must be brought out
  • Neutral grounding method
  • Neutral current transformer requirement

A 50Hz and a 60Hz transformer may require different magnetic design parameters.

Frequency affects core flux density, losses, excitation current and temperature rise. A unit designed for 60Hz may experience overfluxing when incorrectly operated at 50Hz.

The RFQ should clearly state 50Hz transformer or 60Hz transformer.

State the Vector Group

Common vector groups include:

  • Dyn11
  • Dyn5
  • Yyn0
  • YNd11
  • YNyn0
  • Yd11

A Dyn11 transformer is widely used in distribution systems, but it is not a universal default.

The vector group affects:

  • HV-to-LV phase displacement
  • Neutral availability
  • Zero-sequence current path
  • Protection coordination
  • Harmonic performance
  • Parallel operation

When the new unit will operate in parallel with an existing transformer, provide:

  • Existing transformer capacity
  • Voltage ratio
  • Vector group
  • Percentage impedance
  • Tap range
  • Nameplate photograph

Two transformers with different vector groups should not be connected in parallel.

Confirm the Tap Range and Tap-Changer Type

Common off-circuit tap ranges include:

  • ±2 × 2.5%
  • ±5%
  • +2.5% / -7.5%
  • Project-specific ranges

State the required regulating method:

A standard distribution transformer often uses an off-circuit tap changer. Its position can only be changed while the transformer is de-energized.

Projects with wide grid fluctuations and strict LV voltage stability may require an on-load tap changer transformer.

OLTC equipment changes the transformer cost, dimensions, controls, maintenance needs and delivery schedule. It should be specified at the RFQ stage.

Provide the Required Impedance

Percentage impedance may be specified as:

  • 4%
  • 4.5%
  • 5%
  • 6%
  • A calculated project value

Transformer impedance affects prospective short-circuit current and voltage regulation.

Lower impedance generally means:

  • Higher fault current
  • Lower internal voltage drop
  • Higher interrupting-duty requirements for downstream switchgear

Higher impedance generally means:

  • Lower short-circuit current
  • Greater full-load voltage drop
  • Possible motor-starting limitations

When the EPC consultant has completed a short-circuit study, the specified impedance should be included in the RFQ.

When no impedance is stated, the manufacturer may recommend a value based on IEC practice, capacity, voltage and application, but the project engineer should approve the final figure.

Define Loss, Temperature-Rise and Efficiency Requirements

The RFQ should show whether the project is focused mainly on purchase price or lifetime operating cost.

Possible requirements include:

  • No-load loss
  • Load loss
  • Total loss
  • No-load current
  • Temperature-rise limit
  • Sound level
  • Efficiency class
  • Evaluation load factor

A low loss transformer may have a higher initial price but lower long-term electricity cost.

This matters in continuously operated facilities such as:

  • Data centers
  • Hospitals
  • Utility networks
  • Industrial parks
  • Water treatment plants

Ask the supplier to state:

  • Guaranteed no-load loss
  • Guaranteed load loss at reference temperature
  • No-load current
  • Temperature rise
  • Sound pressure level

The guaranteed values should match the final test report.

Identify the Required Transformer Type

Oil-Immersed Transformer

An oil immersed transformer is commonly used for:

  • Outdoor distribution
  • Industrial plants
  • Mines
  • Water projects
  • Utility networks
  • Substations
  • Higher-capacity loads

The RFQ should state:

  • Hermetically sealed or conservator design
  • Mineral oil or natural ester fluid
  • ONAN or another cooling method
  • Fixed or removable radiators
  • Oil-level indicator
  • Pressure-relief device
  • Oil and winding temperature indication

Dry-Type Transformer

A dry type transformer is commonly installed in:

  • Commercial buildings
  • Shopping malls
  • Hospitals
  • Metro systems
  • Data centers
  • High-rise buildings
  • Indoor substations

Provide:

  • Cast-resin or VPI construction
  • Enclosure IP rating
  • Cooling method
  • Temperature controller
  • Fan arrangement
  • Fire and environmental class
  • Room ventilation conditions

Package Substation

A package substation combines an HV section, transformer and LV section.

The buyer should provide:

  • HV incoming arrangement
  • Ring main unit or load-break switch configuration
  • HV protection method
  • LV main breaker rating
  • Number of outgoing feeders
  • Metering requirements
  • Power-factor correction requirements
  • Enclosure material
  • IP rating
  • Cable-entry direction
  • Foundation dimensions

Transformer capacity alone is not enough for a package substation quotation.

outdoor transformer RFQ information.webp

Describe the Installation Environment

Site conditions influence insulation, cooling, enclosure construction and material selection.

Provide:

  • Indoor or outdoor installation
  • Maximum ambient temperature
  • Minimum ambient temperature
  • Daily average temperature
  • Altitude
  • Relative humidity
  • Salt or corrosive atmosphere
  • Dust and sand conditions
  • Seismic requirements
  • Lightning exposure
  • Distance from the coast
  • Transformer-room ventilation

At elevations above 1,000 meters, lower air density affects cooling and external insulation. A high altitude transformer design may be required.

Coastal sites, chemical plants and wastewater facilities may also require:

  • Enhanced anti-corrosion coating
  • Stainless-steel fasteners
  • Anti-condensation heaters
  • IP54 or higher enclosures
  • Sealed terminal boxes
  • Special surface preparation

Late disclosure of these conditions can force major design changes.

Specify the Applicable IEC Requirements

Common requirements include:

  • IEC 60076 transformer
  • IEC 60076-1
  • IEC 60076-2
  • IEC 60076-3
  • IEC 60076-5
  • IEC 60076-10
  • IEC 60076-11 for dry-type transformers
  • Local utility specifications
  • Project technical specifications

State:

  • Applicable standard
  • Project-specific specification
  • Utility requirements
  • Nameplate language
  • Warning-label language
  • Drawing units
  • Document format
  • Third-party certification requirements

Writing only “IEC standard” is not precise enough.

The standard establishes the technical framework, but losses, temperature rise, insulation level, sound level, accessories and project interfaces still require agreement.

oil immersed vs dry type transformer.webp

Provide Insulation and Short-Circuit Data

For medium-voltage and higher-voltage projects, provide:

  • Rated insulation level
  • Power-frequency withstand voltage
  • Lightning impulse withstand voltage
  • System short-circuit level
  • Fault duration
  • Neutral insulation arrangement

An 11kV, 20kV and 33kV network will not use the same insulation data.

When the specification includes a defined lightning impulse withstand voltage, the factory must coordinate the winding insulation, bushings and electrical clearances around that requirement.

System fault level also affects winding mechanical strength. A transformer intended for a high-fault-level network should not be designed from a generic low-duty assumption.

List the Required Accessories

Common oil-transformer accessories include:

  • Oil-level indicator
  • Oil temperature indicator
  • Winding temperature indicator
  • Pressure-relief valve
  • Gas relay
  • Pressure-vacuum gauge
  • Drain valve
  • Oil-sampling valve
  • Earthing terminals
  • Lifting lugs
  • Rollers
  • Marshalling box
  • Silica-gel breather
  • Alarm and trip contacts

Common dry-type accessories include:

  • Temperature controller
  • PT100 sensors
  • Cooling fans
  • Automatic fan control
  • Alarm and trip contacts
  • Enclosure
  • Anti-condensation heater
  • Earthing terminals
  • Rollers

The RFQ should identify accessories as:

  • Standard
  • Optional
  • Mandatory
  • Separately priced

This prevents a low base quotation from being mistaken for a complete supply package.

Define Cable and Terminal Connections

Transformer interfaces must match the site installation.

Confirm:

  • HV bushing, plug-in connector or cable box
  • LV bushing, busbar or cable box
  • Top, bottom or side cable entry
  • Phase sequence
  • Neutral location
  • Cable quantity and cross-section
  • Removable cable-box requirement
  • Busduct interface
  • Flexible-connector requirement
  • Cable-gland requirement

For high-current LV systems, terminal dimensions and busbar arrangement must be approved before manufacturing.

Otherwise, the site may face insufficient bending radius, mismatched busbar holes or inadequate cable-box space.

State the Required Drawings and Documents

Typical document requirements include:

  • General Arrangement Drawing
  • Nameplate Drawing
  • Foundation Drawing
  • Terminal Arrangement Drawing
  • Wiring Diagram
  • Technical Data Sheet
  • Guaranteed Technical Particulars
  • Routine Test Report
  • Packing List
  • Operation Manual
  • Maintenance Manual
  • Spare Parts List
  • Quality Certificate
  • Certificate of Origin
  • Commercial Invoice
  • Final As-Built Drawings

For approval-before-production projects, define:

  • Drawing submission deadline
  • Buyer review period
  • Conditional-approval process
  • Required language
  • PDF, DWG or other formats

Export projects are often delayed by drawing approval and technical clarification rather than by factory production.

Define Routine Tests and FAT Requirements

The RFQ should state whether the project requires:

  • Factory routine testing
  • Witnessed FAT
  • Remote video FAT
  • Third-party inspection
  • Special tests
  • Type-test reports
  • Material certificates
  • Insulating-oil test reports

Common transformer routine tests include:

  • Winding resistance measurement
  • Voltage-ratio and phase-displacement verification
  • Vector-group verification
  • Short-circuit impedance and load-loss measurement
  • No-load loss and no-load current measurement
  • Separate-source withstand test
  • Induced-voltage withstand test
  • Insulation-resistance check
  • Leak test for oil-filled units

Project-specific testing may include:

  • Temperature-rise test
  • Lightning impulse test
  • Sound-level measurement
  • Partial-discharge test
  • Zero-sequence impedance measurement
  • Dissolved-gas analysis
  • Short-circuit withstand evidence

Clarify which tests must be performed on the supplied unit and which may be supported by type-test reports from an equivalent design.

A FAT test requirement affects the production schedule, laboratory booking, inspection cost and delivery date.

When third-party witnessing is required, identify the inspection company, hold points and advance-notice period early.

Provide Packing and Shipping Conditions

“Standard export packing” is too vague for a transformer project.

State:

  • Sea, road or air transport
  • Fully assembled or dismantled shipment
  • Container or break-bulk shipping
  • Destination port
  • Final inland transport distance
  • Road height and weight limits
  • Wooden-case requirement
  • Waterproof wrapping
  • Vacuum packing
  • Moisture absorber
  • Tilt and shock indicators
  • Fumigated wood
  • Long-term outdoor storage requirement

Smaller distribution transformers can often be shipped fully assembled in containers.

Larger transformers may require removal of:

  • Radiators
  • Bushings
  • Conservator
  • Fans
  • Terminal boxes
  • Projecting accessories

Removed components should be numbered, sealed and identified in the packing list and installation drawings.

For oil-filled units, confirm:

  • Oil-filled shipment
  • Nitrogen-filled shipment
  • Transport oil level
  • Separate make-up oil
  • Destination-country oil restrictions
  • Availability of site vacuum-filling equipment

These points are critical in transformer export packaging.

Engineering Case One: Middle East Water-Treatment Project

A Middle East EPC contractor requested two 1600kVA oil-immersed transformers and initially provided:

  • 1600kVA
  • 11kV/415V
  • 50Hz
  • Outdoor installation

Technical clarification later showed that the site was coastal, highly humid and exposed to salt contamination. Maximum ambient temperature was 50°C, and all LV cables had to enter from below.

The final design included:

  • High-temperature capacity verification
  • Enhanced anti-corrosion coating
  • Stainless-steel fasteners
  • Sealed control box
  • Anti-condensation heater
  • Bottom-entry LV cable box
  • High-temperature sealing materials

A quotation based on a standard 40°C inland environment would have required later revision in price, size and delivery.

This case shows why outdoor transformer RFQ information must include climate and installation details.

Engineering Case Two: Commercial Complex Indoor Substation

A commercial complex required three 1250kVA dry-type transformers.

The initial inquiry stated:

  • 11kV/400V
  • Dyn11
  • IP23
  • Indoor installation

A review of the approved LV design showed that the actual system voltage was 415V. The building also used a high proportion of VFD-driven HVAC equipment, elevators and UPS loads.

The factory requested clarification on:

  • Harmonic-load percentage
  • Neutral current
  • Forced-air cooling
  • Temperature alarm and trip settings
  • Enclosure ventilation clearance
  • Fire and sound requirements

The final design used a 415V output and included extra thermal margin for nonlinear loading.

A 400V unit would not have matched the approved distribution system.

This case demonstrates why a dry type transformer inquiry checklist must cover LV voltage, load characteristics and ventilation.

Product Comparison: Oil-Immersed, Dry-Type or Package Substation?

The buyer must define what is being purchased before comparing quotations.

When the site already has HV and LV switchgear and requires a standalone outdoor transformer, an oil immersed distribution transformer may be appropriate.

When the transformer will be installed inside a building and fire performance, space and indoor operation are major concerns, a cast resin dry type transformer may be more suitable.

When the buyer needs a complete HV incoming section, transformer and LV distribution section, the RFQ should cover a prefabricated package substation.

These products cannot be compared by transformer price alone.

An oil-transformer offer may exclude HV and LV switchgear.

A dry-transformer offer may or may not include the enclosure.

A package-substation offer should include the HV unit, transformer, LV unit, enclosure, internal busbars, controls and interlocks.

An unclear supply boundary produces quotations that appear comparable but cover different equipment.

transformer export packaging.webp

Procurement Risk Analysis

Risk 1: Voltage Described Informally

Writing only “11kV transformer” without LV voltage, highest system voltage and insulation level allows suppliers to quote from different design assumptions.

Risk 2: Accessories Assumed to Be Included

Supplier standard accessory packages differ. A low quotation may exclude cable boxes, winding-temperature indication, gas relay, fans or control equipment.

Risk 3: Comparing Only the Total Price

One quotation may be EXW while another includes export packing, inland transport and ocean freight. Prices should be compared under the same trade term.

Risk 4: Late FAT Requirements

Requesting third-party witnessing, temperature-rise testing or impulse testing after production can add cost and delay dispatch.

Risk 5: Ignoring Final-Site Access

A transformer can leave the factory and still fail to reach the installation point. Bridge limits, road height, turning radius and lifting access may require a dismantled shipping design.

Risk 6: Ignoring Drawing-Approval Time

Many EPC projects require approval from the owner, consultant and utility. Manufacturing before approval creates rework risk. Waiting too long for approval compresses the production schedule.

The RFQ should therefore state both the approval process and the required delivery date.

Copy-Ready Transformer RFQ Template

Subject: RFQ for Transformer – [Capacity] – [Voltage Ratio] – [Project Country]

Dear Supplier,

Please provide your technical and commercial quotation based on the following information:

Project name:
Project location:
Application:
Required quantity:
Transformer type: Oil immersed / Dry type / Package substation
Rated capacity:
High-voltage rating:
Low-voltage rating:
Highest voltage for equipment:
Frequency: 50Hz / 60Hz
Phase: Single phase / Three phase
Vector group:
Impedance:
Tap range:
Tap-changer type: Off-circuit / On-load
Cooling method:
Insulation level:
No-load loss requirement:
Load loss requirement:
Temperature-rise limit:
Sound-level requirement:
Installation: Indoor / Outdoor
Maximum ambient temperature:
Minimum ambient temperature:
Altitude:
Humidity and corrosion conditions:
Enclosure protection level:
Cable-entry direction:
HV terminal type:
LV terminal type:
Required accessories:
Applicable standard:
Required routine tests:
Required FAT or third-party inspection:
Required drawings and documents:
Spare-parts requirement:
Packing requirement:
Destination port:
Trade term: EXW / FOB / CFR / CIF / DAP / DDP
Required delivery date:
Warranty requirement:

Please confirm:

  1. Technical compliance and deviations
  2. Guaranteed losses
  3. Included accessories
  4. Drawing-submission schedule
  5. Manufacturing lead time
  6. FAT arrangement
  7. Packing method
  8. Shipping dimensions and gross weight
  9. Warranty scope
  10. After-sales technical support

FAQ

1. Can a buyer obtain a budget quotation with only capacity and voltage?

Yes, but it should be treated as a preliminary estimate. The price may change after impedance, losses, accessories, environment, terminal arrangement and test requirements are confirmed.

2. What should a buyer do when the vector group is unknown?

Confirm it with the project electrical engineer, utility or single-line-diagram designer. Dyn11 is common in distribution systems, but the supplier should not select it without system information.

3. Can an IEC transformer be used in every country?

Not automatically. IEC provides the design and testing framework, while local utilities may impose extra requirements for voltage, efficiency, insulation, labels, connectors and protection.

4. What is the difference between routine testing and FAT?

Routine tests are production tests normally performed on each transformer. FAT is the buyer, consultant or third party’s acceptance process involving test witnessing, document review and inspection.

5. Is the destination port required at the inquiry stage?

It is not essential for an EXW or preliminary FOB price. It is required for CFR, CIF, DAP or DDP calculations.

6. Why does the manufacturer need the maximum ambient temperature?

Ambient temperature affects cooling and thermal margin. A transformer designed for standard conditions may not deliver its full rating continuously in a 50°C environment.

7. Can a new transformer operate in parallel with an existing unit?

Yes, provided the voltage ratio, vector group, impedance, tap position, phase sequence and capacity relationship are compatible.

8. Is wooden-case packing suitable for every transformer?

No. Large units are normally secured with structural steel, waterproof wrapping and separately packed accessories. Wooden cases are more common for bushings, control boxes and smaller units.

9. Should the buyer provide a single-line diagram?

Yes. It helps the supplier confirm voltage levels, grounding, protection, parallel operation and system interfaces.

10. How should quotations from different suppliers be compared?

Compare technical parameters, guaranteed losses, accessories, tests, drawings, packing, trade terms, lead time, warranty and support scope. Total price alone does not show whether the supply boundaries are equal.

Call To Action

For an upcoming oil immersed transformer, dry type transformer, distribution transformer, step-up transformer or package substation project, send us your single-line diagram, technical specification and completed RFQ template.

Our engineering team can review:

  • Capacity and load matching
  • HV and LV voltage configuration
  • Vector group and impedance
  • IEC 60076 requirements
  • Routine tests and FAT scope
  • Export packing and shipping method
  • Drawings and technical documentation

Complete project data allows the manufacturer to provide a more accurate technical proposal, production schedule and commercial quotation.

Make an free consultant

Your Name

Phone Number*

Country*

Remarks

reset